Installation of street lighting in the second stage of the Vezha Complex continues
RIEL Real Estate Corporation continues active construction of the Mistechko Pidzamche Residential Complex. The installation of street lighting in the second stage of the Vezha Complex is underway, and the installation of water pumping station has been completed.
In the third stage, in section 7.3, the laying of internal partitions continues, and in section 7.1, external walls are being arranged.
In the fifth stage, the installation of underfloor networks, including water supply pipelines, electrical cables, as well as cables for the Internet and intercoms, has been completed.