To the news list

Commissioning of elevators in the second stage of the Vezha complex is completed

September 24, 2024

RIEL Real Estate Corporation continues active construction of the Mistechko Pidzamche Residential Complex. In the second stage of the Vezha complex, the commissioning of elevators and installation of fence railings have been completed. The water pumping station is currently under construction.

In the third stage, in section 7.3, the terraces were waterproofed and the roof was filled. In sections 7.2 and 7.3, the façade insulation and finishing is ongoing, and the installation of windows on the inside of the building has already been completed.

In the fifth stage, the road has been completed and the vertical planning of the landscaping is underway.

For more information about the choice of floor and layout, as well as the conditions for purchasing an apartment in the residential complex, please contact our sales department. Contacts are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ЧП «Львівінтерсервіс»

ООО «Вежа на Хмельницького»

ООО «Брама на Хмельницького»

Join our social networks
Contact us in convenient way
(032) 229-54-63
Feedback
The exchange rate as of 10/18/2024 is 41.25 UAH.
Sales departments
Lviv, 116, Bohdana Khmelnytskoho Street
© 2024  Pidzamche. Vezha. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.