To the news list

Façade works are underway in the third stage of the Vezha Complex in section 7.3

April 19, 2024

Real Estate Corporation RIEL reports that the construction of the Mistechko Pidzamche Residential Complex is actively continuing. In the third stage of the Vezha complex, in section 7.3, façade works are underway.

In section 7.1, the ceiling of the 10th floor is made, and the walls are being laid. In section 7.2, windows are being installed and exterior walls are being made.

In the second stage, all sections have been finished with walls and ceilings in the common facilities, and decorative ceilings are being installed.

In the fifth stage, the installation of external water supply and sewerage networks has been completed, and the façade is in the final stages of finishing. The installation of window structures on the first floor of commercial premises is in progress.

You can choose the floor and layout, as well as other details about conditions for purchasing apartments in Mistechko Pidzamche RC in our sales department. Contacts are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ЧП «Львівінтерсервіс»

ООО «Вежа на Хмельницького»

ООО «Брама на Хмельницького»

Join our social networks
Contact us in convenient way
(032) 229-54-63
Feedback
The exchange rate as of 5/9/2024 is 39.51 UAH.
Sales departments
Lviv, 10, Volodymyra Velykoho Street
© 2024  Pidzamche. Vezha. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.