In the third stage in section 7.1, the laying of walls continues
RIEL Real Estate Corporation reports that the construction of the Mistechko Pidzamche Residential Complex is actively underway. In the third stage of the Vezha Complex, in section 7.1, the laying of walls and the installation of a roof screed continues.
In section 7.2, façade works and window installation are underway. In section 7.3, the facade is being finished.
The second stage is nearing completion of the fence railing installation. Landscaping of the territory is completed.
In the first stage, cleaning inside the buildings is underway.
In the fifth stage, the backfilling of the sinuses of all sections is underway, and the internal wiring of power supply cables to the apartments and the common facilities has been completed.