Construction Progress Update
We continue to share updates on the progress of construction at the Vezha Residential Complex — part of the large-scale Mistechko Pidzamche development project.
Third Stage
In Section 7.3, installation of internal partitions has been completed, and plastering works have begun.
In Section 8.1, preparations for plastering works in common areas are underway, and installation of the fire alarm system is in progress.
Fifth Stage
On the first floor, preparations are underway for the installation of a Grilyato-type suspended ceiling.
Work is also being carried out to prepare for the installation of stairwell railings.
In addition, delivery of the elevator equipment is expected soon.
The Vezha Residential Complex is a modern part of the large-scale Mistechko Pidzamche development in Lviv, combining comfort, high-quality design, and its own infrastructure. The project features cozy apartments, thoughtfully designed public spaces, and everyday conveniences. The architecture of the complex blends contemporary style with functionality, while the landscaping creates an atmosphere of comfort and safety for residents. Vezha is the perfect choice for those who value comfortable living in a dynamic urban environment.