Construction Progress Update
Construction of the Vezha Residential Complex continues — we are pleased to share the latest updates from the site. The Vezha is part of the large-scale development project Mistechko Pidzamche.
In the third stage, Section 8.1, plastering works are ongoing in common areas, and installation of water supply and heating systems is in progress. The installation of the fire alarm system has been completed.


In Section 7.3, plastering works have been completed from the 10th to the 3rd floor. At the same time, installation of the water supply and internal power supply systems is underway.
In the fifth stage, installation of stairway railings and handrails is in progress, and preparations for landscaping of the surrounding area have begun.
The Vezha Residential Complex is a modern part of the large-scale Mistechko Pidzamche development in Lviv, combining comfort, thoughtful planning, and its own infrastructure. The project features cozy apartments, public spaces, and everyday conveniences. Its architecture blends contemporary style with functionality, while the landscaped surroundings create an atmosphere of comfort and safety.