Mistechko Pidzamche RC: in the section А-1 of the first stage of Vezha RC, the seventh floor is equipped with a slab

July 14, 2021

RIEL Real Estate Corporation reports that the construction of Vezha RC as part of the construction of Mistechko Pidzamche RC facility is actively pursued. Now, the seventh floor of section A-1 is equipped with a slab. This was announced by the head of the construction project Ivan Chykh.

It is also reported that in section А-2 the laying of the outer walls is underway and the roof covering has been completed. In the section А-3, the installation of window structures is being completed, the builders are engaged in facade insulation.

In the section А-4, the glass facade is being set up and the walls are being laid.

Also, according to the project manager, in section A-5, the laying of internal walls and the arrangement of the glass façade continues, and in section A-6, the laying of external walls is being carried out.

The improvement of the local area continues on a scheduled basis.

You can choose the floor and layout, as well as find out about other details on the terms for purchasing an apartment in Mistechko Pidzamche RC in our sales departments. Our managers will be happy to advise you on any issue. Contacts at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ЧП «Львівінтерсервіс»

ООО «Вежа на Хмельницького»

ООО «Брама на Хмельницького»

Join our social networks
Contact us in convenient way
(032) 229-54-63
Feedback
The exchange rate as of 4/27/2024 is 39.67 UAH.
Sales departments
Lviv, 10, Volodymyra Velykoho Street
© 2024  Pidzamche. Vezha. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.