In section А-1 of the first stage of Vezha residential complex, the vertical of the ninth floor is in progress
RIEL Real Estate Corporation reports that the construction of Vezha residential complex is actively pursued. In section А-1, the vertical of the ninth floor is in progress. This was announced by the project manager Ivan Chykh.
We would also like to report that in section А-2, the laying of external and internal walls continues. In section А-3, the installation of window structures has been completed, the insulation of the facade continues.
In section А-4, window structures and the glass facade of the building are being arranged.
Besides, according to the project manager, in section A-5, the laying of internal walls continues, the installation of window structures is being completed, the facade is being finished, and in section A-6, the roof is being arranged, and the laying of the boiler room is completed.
The improvement of the local area continues on a scheduled basis.