In the third stage of complex in section 8.1, the façade has been completed

July 20, 2023

RIEL Real Estate Corporation reports that the construction of Mistechko Pidzamche RC is actively pursued. In the third stage of Vezha complex in section 8.1, the façade has been completed. In sections 7.2 and 7.3, walls are being laid.

In the second stage, the installation of railings is being completed, the installation of elevators is being carried out.

In the first stage, the launch of water supply to the risers has been completed in all sections, the installation of elevators is underway.

In the fifth stage in section 10.1, the installation of window structures has been completed, the façade is being insulated and finished.

You can choose the floor and layout, as well as find out other details on the conditions for purchasing an apartment in Mіstechko Pidzamche RC, in our sales department. Contacts at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ЧП «Львівінтерсервіс»

ООО «Вежа на Хмельницького»

ООО «Брама на Хмельницького»

Join our social networks
Contact us in convenient way
(032) 229-54-63
Feedback
The exchange rate as of 11/22/2024 is 41.35 UAH.
Sales departments
Lviv, 116, Bohdana Khmelnytskoho Street
© 2024  Pidzamche. Vezha. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.