Blockwork on the first floors has been completed in sections 7.2 and 7.3 of the third stage
RIEL Real Estate Corporation announces that in the third stage of the Vezha complex, the membrane installation on the roof of section 7.1 has been completed. In sections 7.2 and 7.3, the blockwork of the first floors has been completed, and in section 7.3, the waterproofing of the terrace walls is nearing completion.

In the fifth stage, interior finishing works are continuing: plastering of walls in common areas is being carried out, and the installation of tiles on the floors of corridors and staircases has begun.